Broadway Subway project progress updated

November 24, 2022 at 5:03 pm  BC, News, Politics, Provincial

Work on the Broadway Subway project has reached another milestone with the imminent launch of the second tunnel-boring machine for the new rapid transit line.

The first machine launched Oct. 7, 2022, and has made significant progress toward its first breakthrough at Mount Pleasant Station, while the second machine is now fully assembled and set to launch.

Named Elsie and Phyllis, after two influential British Columbians, the custom-designed tunnel-boring machines measure about six metres in diameter, 150 metres in length and weigh almost one million kilograms each. Named for Elizabeth (Elsie) MacGill and Phyllis Munday, the machines were manufactured in Germany, shipped to Canada in spring 2022, and assembled on concrete slabs at the launch site near Great Northern Way.

A five-week strike in June 2022 affected the concrete supply in the Lower Mainland, which affected the start of tunnel boring. As a result, the overall schedule for project completion has been moved from late 2025 into early 2026. A precise update on the project timeline will be provided in the spring of 2023 when station excavation and tunnel boring are further advanced. The project remains within budget.

Progress continues to be made on tunnelling work; more than half of the columns for the guideway between VCC-Clark and Great Northern Way-Emily Carr Station are complete. Construction and fit out of the stations and tracks will begin once tunnel boring has finished.

The Broadway Subway will extend the Millennium Line from VCC-Clark Station to the future Broadway and Arbutus station, providing fast, convenient SkyTrain service along the Broadway corridor, home to B.C.’s second-largest jobs centre, world-class health-care services, an emerging innovation and research hub, and growing residential communities.

The project will result in faster travel, better access and fewer cars on the road in this heavily used corridor. Once in service, the trip from VCC-Clark to Arbutus Station will take 11 minutes, saving the average transit commuter almost 30 minutes a day and relieving congestion along Broadway.

The Broadway Subway will also support new transit-oriented developments, which create efficient, livable communities and maximize the opportunities provided by the investment government is making in public transit.

It’s estimated the Broadway Subway project will create more than 13,000 direct and indirect jobs during construction, supporting economic development within the region and beyond.

Learn More: 

Broadway Subway project: https://www.broadwaysubway.ca

Photos of the tunnel boring machines and general construction images can be found here:
https://www.flickr.com/photos/bcgovphotos/albums/72177720302678825

Job opportunities for the Broadway Subway project: https://www.bcib.ca
 

View the full article from the original source

No conversations yet

Activity Stream

Thu, Apr 18, 2024 at 8:00 am - David Suzuki posted on their blog: Igniting the great global transformation
Thu, Apr 11, 2024 at 4:00 am - David Suzuki posted on their blog: Carbon pricing 101: How it works!
Thu, Apr 4, 2024 at 8:00 am - David Suzuki posted on their blog: Carbon pricing is good for the climate and affordability
Thu, Mar 28, 2024 at 8:00 am - David Suzuki posted on their blog: Climate change, water and ice are inextricably linked
Thu, Mar 21, 2024 at 8:00 am - David Suzuki posted on their blog: Fossil fuel industry gaslighting puts world at risk
Thu, Mar 14, 2024 at 8:00 am - David Suzuki posted on their blog: Alberta adds fuel to the climate crisis fire
Thu, Mar 7, 2024 at 11:30 am - Doug Smith posted on their blog: KamloopsTrails.ca – Kamloops Trails
Thu, Mar 7, 2024 at 8:00 am - David Suzuki posted on their blog: Valuing exponential growth as “progress” is unsustainable
Tue, Mar 5, 2024 at 8:30 am - Doug Smith posted on their blog: Ridge Lakes on Spikes – Kamloops Trails
Full Stream